Real Vancouver basement finish with bathroom & wet bar estimate

How Much Does It Cost to Finish a Basement with Bathroom and Wet Bar in Vancouver?

Typical estimate for this project
$41,258.90
Possible Extra
$1,050.00
Your estimate may differ — get a personalized estimate below.

A 300 sqft basement finish with a 3-piece bathroom and wet bar in Vancouver typically ranges from $33,000 to $49,600. This includes concrete slab trenching for new plumbing, framing, drywall, LVP flooring, quartz countertop, electrical, HVAC extensions, permits, and all finish trades. Finish fixtures (toilet, vanity, cabinets, bar fridge) are owner-supplied.

Chat with us, get a price in minutesView breakdown
Calculate project costs in minutes. We only share your project details with a contractor when you ask to be connected.
Unfinished basement with exposed concrete foundation walls, ceiling joists, and a walk-out sliding door ready for finishing
Is this like your project?

Location

Vancouver, BC


Property type

Detached house (2000 build)


Existing condition

Unfinished basement, bare concrete walls, exposed joists


New bathroom

3-piece (toilet, sink, acrylic shower stall)


Wet bar

10 lft run, quartz countertop, bar fridge


Finishing fixtures

Owner-supplied

Cost breakdown

Where the $41,259 project cost goes

Where the $41,259 project cost goes

See the full cost breakdown for this project.

Scope itemLabourMaterialsTotal
Site Protection Setup$100.00$75.00$175.00
Building Permit Administration$225.00$225.00
Plumbing Permit Administration$326.25$326.25
Electrical Permit Administration$303.75$303.75
Permit Fee Allowance$1,150.00$1,150.00
Project Management & Trade Coordination$2,400.00$2,400.00
Framing Layout$100.00$100.00
Concrete Slab Trenching$1,740.00$225.00$1,965.00
Below-Slab Drainage & Concrete Patching$1,160.00$425.00$1,585.00
Perimeter & Partition Framing$1,200.00$950.00$2,150.00
Electrical Rough-In Wiring$3,240.00$675.00$3,915.00
Plumbing Above-Slab Rough-In$2,320.00$650.00$2,970.00
Bathroom Exhaust Fan Installation$362.50$220.00$582.50
Heating Duct Extensions$580.00$225.00$805.00
Fiberglass Wall Insulation$2,000.00$448.00$2,448.00
Vapor Barrier and Air Sealing$1,000.00$162.40$1,162.40
Drywall Install & Level 4 Finish$2,000.00$975.00$2,975.00
Shower Stall Installation$870.00$870.00
Interior Painting$2,405.00$1,475.00$3,880.00
Luxury Vinyl Plank Flooring$1,950.00$2,100.00$4,050.00
MDF Baseboard Installation$585.00$126.00$711.00
Quartz Countertop Supply & Install$297.50$2,200.00$2,497.50
Wet Bar Cabinet Installation$297.50$297.50
Plumbing Fixtures Finish$870.00$225.00$1,095.00
Recessed LED Lighting$675.00$550.00$1,225.00
Switches & Receptacles Finish$270.00$100.00$370.00
Bar Fridge Installation$50.00$50.00
Final Post-Construction Cleanup & Disposal$500.00$475.00$975.00
Complete base project cost$27,827.50$13,431.40$41,258.90
Total Cost

$41,258.90

Possible extra

$1,050.00

On-site decisions or hidden conditions that could increase the scope.

What's your home project?

Get an estimate, then choose to connect with pros

Things to know

Things to know for your project

Things to know for your project

Conditions, constraints, and on-site decisions that shape the final project cost.

Slab condition surprises

Trigger: During demo, the concrete slab is more deteriorated or thicker than expected, requiring additional cutting or disposal.

Add $300–$600 for extra demo labor and disposal fees.


Moisture issues behind walls

Trigger: When walls are opened, evidence of past moisture or efflorescence is found on the foundation wall interior.

Add $500–$1,200 for dimpled membrane vapor barrier, perimeter drainage channel, or a standalone dehumidifier rough-in.


Main sewer line connection complexity

Trigger: The existing main stack is cast iron and requires a fernco transition, or the slab depth makes tying into the sewer more labor-intensive.

Add $200–$500 for specialty couplings, deeper excavation, or additional below-slab fittings.


Owner-supplied fixture delays

Trigger: Finish fixtures (toilet, vanity, shower kit, cabinets) arrive late, are backordered, or have incorrect dimensions.

Add $75–$150 per rescheduled trade visit and push project completion by 1–3 weeks.

How the estimate was created

The real conversation behind this estimate

The real conversation behind this estimate

This is the how RenoFiz gathered the facts and turned a simple request into a scoped estimate.

Homeowner

I want to finish my basement building a new large recreation room, a new bathroom and a wet bar.

RenoFiz

Hi there! I'm Chris, a General Contractor with 25 years of experience in residential construction. I'd love to help you plan out and budget this basement project.

Looking at your photo, you have a fantastic clean slate to work with. The unfinished space has great height, exposed ceiling joists that will make running electrical and HVAC ducting straightforward, concrete walls ready for framing/insulation, and a wonderful walk-out sliding door that brings in plenty of natural light.

To make sure we capture everything you want and build an accurate scope, we’ll walk through your project step-by-step, starting with the most trade-complex parts:

  1. The New Bathroom (Highest complexity: plumbing drainage, venting, electrical, framing, waterproofing, tile, and fixtures)
  2. The Wet Bar (Medium-high complexity: plumbing supply/drain lines, cabinetry, countertops, backsplash tile, and electrical)
  3. The Recreation Room (Medium complexity: perimeter framing, wall/ceiling insulation, drywall, electrical/lighting layout, flooring, and paint)

To kick things off and start calculating our primary quantities, I have a few initial questions:

Question: Could you please provide your postal code? This helps us check local building permit guidelines, utility hints, and regional pricing.

Question: For the new bathroom, what fixtures are you planning to incorporate? (e.g., toilet, vanity sink, and a shower, bathtub, or both?)

Question: What is the approximate square footage (or length and width) of the basement area you want to finish?

Question: For the wet bar, what features are you imagining? (e.g., sink, cabinets, countertop, bar fridge, or wine cooler?)


Photos that would help

While your overview photo is excellent, as we go along, it would be extremely helpful if you could share:

  • The plumbing rough-in area: Do you have existing plumbing pipes (rough-ins) protruding from the concrete floor for a future bathroom or wet bar, or will we need to break concrete to run new drain lines?
  • The electrical panel: A photo of your main breaker panel (with the door open so we can see the labels and capacity) to check if we have space for the new bathroom circuits, wet bar appliances, and recreation room lighting.
Homeowner

Could you please provide your postal code? This helps us check local building permit guidelines, utility hints, and regional pricing.: V5K

For the new bathroom, what fixtures are you planning to incorporate? (e.g., toilet, vanity sink, and a shower, bathtub, or both?): a sink, a toilet and a shower

What is the approximate square footage (or length and width) of the basement area you want to finish?: 20ft x 15ft

For the wet bar, what features are you imagining? (e.g., sink, cabinets, countertop, bar fridge, or wine cooler?): sink, cabinets, countertop and bar fridge

Anything Else? (Optional): I don't have any plumbing for a bar or bathroom. my electric panel is 200A.

RenoFiz

Thank you! That is incredibly helpful. Knowing you have a 200A electrical panel is great news—it means we have plenty of electrical capacity for all your additions without needing a costly service upgrade.

Because you do not have existing plumbing rough-ins, our plumber will need to sawcut the concrete slab, excavate, lay down the drain pipes, tie them into your main sewer stack, and repour concrete to patch the floor. This is a vital detail that we will build directly into your estimate.

To help me dial in the design, material costs, and trade coordination, please let me know your thoughts on the following details:

Question: What year was the home built, and is it a detached single-family home, duplex, or townhouse?

Question: For the bathroom shower, are you looking for a standard acrylic shower stall kit or a custom-tiled shower with a waterproof membrane?

Question: What is the planned length of your wet bar cabinet run, and what material would you prefer for the countertop (e.g., laminate, quartz, granite, butcher block)?

Question: Will the new bathroom and the wet bar be located adjacent to each other (sharing a wall) and close to where your main sewer stack exits the house?

Question: What type of flooring would you prefer for the recreation room (e.g., Luxury Vinyl Plank (LVP), laminate, carpet)? Also, would you prefer a drywall ceiling or a drop/suspended ceiling?

Question: For the finish items (toilet, vanity, faucets, sink, shower fixtures, bar cabinets, bar fridge), do you intend to purchase these yourself (owner-supplied) or would you like the contractor to supply them?

Homeowner

What year was the home built, and is it a detached single-family home, duplex, or townhouse?: 2000. detached house.

For the bathroom shower, are you looking for a standard acrylic shower stall kit or a custom-tiled shower with a waterproof membrane?: standard acrylic shower stall kit

What is the planned length of your wet bar cabinet run, and what material would you prefer for the countertop (e.g., laminate, quartz, granite, butcher block)?: 10ft , quartz countertop

Will the new bathroom and the wet bar be located adjacent to each other (sharing a wall) and close to where your main sewer stack exits the house?: yes they are going to share a wall and close to the main sewer stack

What type of flooring would you prefer for the recreation room (e.g., Luxury Vinyl Plank (LVP), laminate, carpet)? Also, would you prefer a drywall ceiling or a drop/suspended ceiling?: LVP flooring. drywall ceiling with pot lights.

For the finish items (toilet, vanity, faucets, sink, shower fixtures, bar cabinets, bar fridge), do you intend to purchase these yourself (owner-supplied) or would you like the contractor to supply them?: I'll purchase the items.

RenoFiz

Your project estimate

Project summary

Finish a 20ft x 15ft unfinished basement area in a 2000-built detached house, adding a new 3-piece bathroom (toilet, sink, acrylic shower) and a 10ft wet bar sharing a plumbing wall near the sewer stack. Concrete slab trenching is required for drainage. All finishing fixtures, cabinets, and appliances are owner-supplied; countertop is quartz, flooring is continuous LVP, and ceiling is drywall with 10 LED pot lights. City of Vancouver building, electrical, and plumbing permits are required.

Estimate range

$32,100 - $48,300 This is a starting ballpark, not a final price.

Estimated work

ItemDetailsRange
Site Protection SetupPREP floor and corridor dust protection from main entry to basement work area.$125 - $225
Building Permit AdministrationPREP, submit, and coordinate City of Vancouver Building Permit application and inspections.$175 - $275
Plumbing Permit AdministrationPREP, submit, and coordinate City of Vancouver Plumbing Permit application and inspections.$250 - $400
Electrical Permit AdministrationPREP, submit, and coordinate City of Vancouver Electrical Permit application and inspections.$225 - $375
Permit Fee AllowanceCarry mandatory permit fee allowances for City of Vancouver municipal building, plumbing, and electrical permits.$900 - $1,400
Project Management & Trade CoordinationGC project coordination, sequencing, trade handoffs, and schedule management for 7 active trades.$1,900 - $2,900
Framing LayoutPREP and lay out walls, partitions, and wet bar footprint on the concrete slab.$75 - $125
Concrete Slab TrenchingDEMO concrete slab, sawcut, jackhammer, and excavate for new below-slab plumbing lines (15 lft).$1,550 - $2,400
Below-Slab Drainage & Concrete PatchingINSTALL below-slab drainage pipe, tie into sewer stack, backfill, and repour concrete to patch the slab.$1,250 - $1,950
Perimeter & Partition FramingINSTALL wood framing for 70 lft of perimeter walls, 13 lft of bathroom partitions, and ceiling ductwork soffits.$1,700 - $2,600
Electrical Rough-In WiringINSTALL rough-in electrical circuits for 10 LED pot lights, bathroom circuits, exhaust fan, wet bar, and receptacles.$3,100 - $4,700
Plumbing Above-Slab Rough-InINSTALL rough-in water lines and drains for shower, toilet, bathroom sink, and wet bar sink.$2,300 - $3,600
Bathroom Exhaust Fan InstallationINSTALL bathroom exhaust fan and vent ducting to the exterior.$450 - $700
Heating Duct ExtensionsINSTALL sheet metal heating duct run-outs with registers extended from the existing trunk line.$600 - $1,000
Fiberglass Wall InsulationINSTALL fiberglass wall insulation on 560 sqft of perimeter walls.$1,900 - $3,000
Continuous Poly Vapor BarrierINSTALL continuous 6-mil poly vapor barrier and acoustical sealant on insulated walls.$100 - $200
Drywall Install & Level 4 FinishINSTALL, tape, mud, and sand drywall to Level 4 finish on 1,068 sqft of wall and ceiling surfaces, including primer.$2,300 - $3,600
Shower Stall InstallationINSTALL owner-supplied standard acrylic shower stall kit, including base, panels, and doors.$650 - $1,050
Interior PaintingPAINT basement walls, ceiling, baseboards, and door trim (two coats). Eggshell on walls, flat on ceiling, semi-gloss on trim.$3,100 - $4,700
Luxury Vinyl Plank FlooringINSTALL Luxury Vinyl Plank (LVP) flooring and underlayment across 300 sqft basement footprint.$3,200 - $4,900
MDF Baseboard InstallationINSTALL 90 lft of MDF baseboards in recreation room and bathroom.$550 - $900
Quartz Countertop Supply & InstallSUPPLY and INSTALL 10 lft of quartz countertop with undermount sink cutout and polished edges.$1,900 - $3,000
Wet Bar Cabinet InstallationINSTALL owner-supplied wet bar cabinets (10 lft run).$225 - $375
Plumbing Fixtures FinishINSTALL owner-supplied bathroom toilet, single-sink vanity, faucet, wet bar undermount sink, and wet bar faucet.$850 - $1,350
Recessed LED LightingINSTALL 10 recessed LED pot lights in recreation room, bar, and bathroom.$950 - $1,500
Switches & Receptacles FinishINSTALL finishing electrical switches, standard receptacles, and cover plates.$275 - $450
Bar Fridge InstallationINSTALL and test owner-supplied under-counter bar fridge.$40 - $60
Final Post-Construction Cleanup & DisposalPREP post-construction cleanup and SUPPLY 14-yd debris bin rental for safe waste disposal.$750 - $1,200

Cost summary

CategoryRange
Materials$10,700 - $16,200
Labour$21,400 - $32,200
Total$32,100 - $48,300

What is included

  • Set up floor and corridor protection from main entry to basement work area.
  • Obtain building, plumbing, and electrical permits from City of Vancouver.
  • Lay out bathroom partition walls, wet bar footprint, and recreation room boundaries on concrete slab.
  • Sawcut, jackhammer, and excavate concrete slab for new bathroom (shower, toilet, sink) and adjacent wet bar drainage lines (approx. 15 lft trench).
  • Install below-slab drain piping, tie into main sewer stack, backfill trench, and pour new concrete to patch the slab.
  • Frame 70 lft of perimeter walls against concrete foundation, 13 lft of bathroom partition walls, and soffits around ceiling ductwork.
  • Rough-in electrical circuits for 10 LED pot lights, bathroom lights/GFCI, exhaust fan, wet bar fridge/outlets, and recreation room perimeter receptacles.
  • Rough-in water supply lines and drain/vent piping for bathroom (shower, toilet, sink) and wet bar sink.
  • Rough-in bathroom exhaust fan ducting and extend forced-air heating duct run-outs with registers from existing trunk line.
  • Install 560 sqft of perimeter wall insulation (rigid foam/batt) and vapor barrier as per BC Building Code.
  • Inspect electrical, plumbing, HVAC, and framing rough-ins (City of Vancouver inspections).
  • Hang, tape, mud, and sand drywall on all walls and ceiling (approx. 1,068 sqft of board surface), including paint priming.
  • Install owner-supplied standard acrylic shower stall kit.
  • Paint walls, ceiling, and trim in bathroom, wet bar, and recreation room (eggshell on walls, semi-gloss on trim/doors).
  • Install continuous Luxury Vinyl Plank (LVP) flooring with underlayment across the entire 300 sqft basement footprint.
  • Install owner-supplied wet bar cabinets (10 lft) and coordinate template/install of 10 lft quartz countertop with undermount sink cutout.
  • Install owner-supplied plumbing fixtures (toilet, vanity, vanity faucet, wet bar sink, and wet bar faucet).
  • Install electrical finish trim (switches, cover plates, 10 LED pot lights, and light fixtures).
  • Set up owner-supplied bar fridge and complete final testing.
  • Conduct final building, electrical, and plumbing inspections.
  • Perform final post-construction cleanup and haul away project debris.

Permits or inspections

ItemWhy it may be needed
Building permit (interior renovation)Required by City of Vancouver for finishing an unfinished basement and creating new rooms/walls.
Electrical permitRequired for roughing in and finishing new electrical circuits, outlets, and fixtures.
Plumbing permitRequired for installing new drain waste vent (DWV) piping below slab and tying in bathroom/bar fixtures.

Possible add-ons

These items are not included in the estimate range above. They may change after an on-site review.

ItemTradePossible rangeWhat would confirm it
Replace main house or fixture shutoff valves if existing municipal water valves are seized or fail to hold water when plumbing connections are started.Plumber$200 - $300Plumber identifies that the main house water shut-off or fixture shut-off is seized or leaking upon demolition.
Supply and apply self-leveling underlayment compound over concrete slab if uneven pitting, slopes, or high-spots exceed tolerance for click-LVP.Flooring Specialist$350 - $550After demolition or during surface preparation, significant subfloor un-levelness or concrete pitting is identified.
Cut and flash a new exterior wall or roof penetration if no existing passive duct venting path exists for the bathroom exhaust fan.HVAC Technician$275 - $425If no existing duct or exterior venting pathway exists, cutting a new exterior wall or roof penetration is required for the exhaust fan.

You can keep chatting to ask questions or adjust the project — and when you're ready, a real professional will confirm the details and discuss final pricing with you, typically after seeing the space in person.

The Request a Pro button is now active — press it to connect with a local contractor for an on-site visit and firm quote.

Related projects

View Other Estimates

View Other Estimates

See other projects in Vancouver or in related trades.

Basement Finishing
Vancouver, BC
Single rec room finish
How Much Does It Cost to Finish a Basement Rec Room in Vancouver?

This Vancouver homeowner wanted to finish their 20ft × 15ft unfinished basement into a large recreation room. The home was built in 1990 or newer, is a single-family detached house, and the basement has been completely dry with no history of moisture issues. The scope includes a drywall ceiling with bulkheads, LVP flooring, 8 LED pot lights, a storage closet under the stairs, and standard permit administration.

View project cost details